T1, T2 and T3 mold trials: what each sample round should prove and what to check
October 29, 2026
T1 is the first set of parts made from a new mold, T2 is the set after the first round of corrections and T3 is the set after the second. Each round should prove something specific. T1 proves the mold fills, closes, ejects and makes recognizable parts. T2 proves the corrections worked and the dimensions are converging. T3 proves the mold and process are stable enough to approve for production. Naming varies by plant, so agree the definitions before the mold is built.
What a trial round is for
A new mold is a precision tool built from a design on paper. It will not be perfect on the first shot. Fill patterns, shrinkage, cooling and venting behave differently from the simulation or the drawing, and the mold maker needs real parts to tune the steel. A trial round is a controlled test: run, measure, compare to the drawing, decide what to change in the mold or the process.
The buyer’s job is to define what a pass looks like and to check the evidence, not just the parts. Without agreed criteria, trials turn into opinion.
Round summary
| Round | Main question | Typical output | Typical decision |
|---|---|---|---|
| T0 (if used) | Does the mold function at all? | A few shots, often short or unfinished | Internal plant fix before you see anything |
| T1 | Does it make a part? | First samples, photos, a basic dimensional report | List corrections to the mold and process |
| T2 | Did the corrections work? | Samples after steel changes, full dimensional report | Approve, or ask for one more round |
| T3 | Is it stable and within spec? | Samples on a defined process, capability data if required | Approve for production or run first article inspection |
Some plants label rounds differently, for example counting trial runs by the number of mold modifications. Ask the plant to define each round in its quote.
T1: does the mold work
T1 is run after assembly and basic polishing. Expect problems, and judge T1 on how well the plant diagnoses them.
What T1 should prove:
- The mold closes without damage and the cooling does not leak.
- The cavity fills without short shots at a reasonable pressure.
- The part ejects cleanly, without sticking or deformation.
- The gate and runner work as designed, and the hot runner zones control.
- The part is the right shape, with all features present.
- Material and color are as specified.
What to expect: flash at the parting line, sink marks, some warpage, dimensions outside tolerance in several places, unpolished areas. These are normal. See injection molding defects: causes and fixes for how to read them.
What to ask for with T1:
- Photos of the parts, the mold open and the machine.
- A basic dimensional report on the critical features, even if many are out of tolerance.
- The process sheet: melt and mold temperatures, pressures, speeds, cycle time.
- A list of planned mold corrections, with dates.
- Sample weight, and the resin lot and drying record.
If a plant ships T1 samples with no report, no photos and no correction list, you cannot tell whether it understands the problems. The sample report is covered in T1 sample reports for export buyers.
T2: did the corrections work
By T2 the mold maker has adjusted steel: opened or closed gates, changed vents, adjusted dimensions with the steel-safe allowance, re-polished and fixed flash. The process is closer to its final window.
What T2 should prove:
- Every correction from the T1 list was done and its effect is measured.
- Critical dimensions are within tolerance, or the remaining gap is understood and has a plan.
- Cosmetic faces match the finish and texture specification.
- Fit and function work in a test assembly with the mating parts.
- Cycle time is close to the quoted figure.
- The process is stable across a short run: several consecutive shots with similar weight and dimensions.
What to ask for with T2:
- A full dimensional report on all marked features, with the sample size you agreed. One part is a story, not data.
- A comparison to T1, so you see the trend.
- A cavity-by-cavity report for multi-cavity molds.
- Assembly check photos or a fit test result.
- A short list of what is still open.
Many molds pass at this stage. If so, approve in writing and move to first article inspection. See first article inspection for plastic parts.
T3: is it stable and ready for production
T3 is needed when T2 leaves open issues, when the part is critical, or when you require capability proof. At this stage the focus moves from the mold to the process.
What T3 should prove:
- All out-of-tolerance dimensions from T2 are fixed.
- The process window is defined: parameter ranges within which the part stays good.
- A longer run shows stability. For critical features, capability data such as Cpk from a consecutive shot sample. See Cpk in injection molding.
- Appearance holds up over the run, with no new defects.
- The process is documented well enough that another operator or press could reproduce it.
- Packaging and labeling meet the order.
At this stage you may also require approval steps like PPAP if you work in automotive. See PPAP in injection molding.
Need a quote for a molded part? Get matched with a molding plant
What to measure on every round
- Critical-to-quality dimensions from the drawing, with measurement method stated.
- Part weight. A quick check of fill consistency. Weight variation across shots shows a process that is not stable.
- Cosmetic faces, against agreed limit samples. See limit samples for cosmetic defects.
- Fit and function with the mating part, in a real assembly where possible.
- Material: grade, color and certificate, and a test for key properties if required.
- Cycle time and key process parameters.
Measure after the parts have settled to room temperature and the conditioning time agreed. Measuring a warm part gives a false picture. For tolerances by resin, see injection molding tolerances.
Mold changes between rounds
Between rounds, the mold maker changes the steel. The usual changes are:
- Removing steel to bring dimensions to nominal, which is why the mold was cut steel-safe.
- Adjusting gates, runners and vents.
- Polishing or texturing.
- Modifying cooling.
- Fixing flash with parting line work or shutoffs.
- Welding and re-cutting where steel must be added, which is slower and carries risk.
Ask for a log of what was changed in each round and why. Keep it with the mold records. It is the history anyone will need if the mold moves plants later, as described in the injection mold transfer checklist.
Approval: what you are signing
Approval means you accept the mold and process as capable of making parts to your specification. Be clear in writing:
- Which samples and which revision of the drawing were approved.
- The process sheet that was approved.
- The resin and color, and the allowed alternatives.
- Known deviations that you accepted, and the limits.
- Who owns the next step, such as first article inspection or a pilot lot.
Do not approve with a long list of verbal promises. If a defect is open, write it into the approval with a due date and a check.
Common mistakes
- Approving on looks. A part that looks right can be out of tolerance or made on a fragile process.
- No agreed criteria. Opinions replace measurement.
- Not asking for the process sheet. Without it, the plant cannot reproduce the sample later.
- Skipping the mold design review. Many T1 problems start in design. A review before steel is cut prevents them. See mold design review checklist.
- Late design changes. A change after T1 means another round and sometimes new steel work.
- Too few parts measured. Sample size should match the risk. Agree it up front.
Planning the schedule
Plants differ, but a sensible plan allows time for each round: shipping the samples, your review and the correction work. If samples travel overseas, add transit time for each round, and ask whether the plant can send photos and measurement data ahead of the parcel so corrections can start sooner. Include the trial rounds in the project plan from the start, because they set the date for production orders.
Next step
If you want a plant that agrees the round definitions and the sample report in the quote, send an RFQ with your drawing and acceptance criteria. We are a manufacturers’ representative for audited plastic injection molding plants. We match your request to the one partner plant whose lane fits, you order from that plant directly, and it costs the buyer nothing. The plant pays us a commission on orders from buyers we introduce.
Frequently asked questions
How many mold trials are normal before production?
Most molds need a T1 and one or two correction rounds, so two to three trials. Simple molds can pass on T1 with only minor adjustments. Complex parts, tight tolerances, new resins or cosmetic surfaces often need more. Ask the plant how many rounds the mold price includes and what each extra round costs.
Should I approve T1 samples if they look good?
Not on appearance alone. T1 samples can look fine and still be outside tolerance, short on weight or made on a process that cannot repeat. Check the dimensional report, material certificate, weight and the process sheet before approving. Treat approval as a decision about repeatability, not about the sample in your hand.
Who pays for the correction rounds after T1?
It depends on the quote. Many quotes include a set number of rounds. Corrections caused by a plant error are normally the plant's cost, while changes you request after approving the design are normally yours. State the number of rounds included and who pays for design changes in the purchase order, not by email afterwards.