A T1 sample report is the document package that goes with the first parts from a new mold. Overseas buyers accept it when it is complete, readable without a phone call and honest about problems. It should include a ballooned drawing, a dimension table with measured values per cavity, the process settings used, material details, photos and a clear list of what will change before the next trial. This guide describes what to include and how to present it so the buyer can approve or reply the same day.
What T1 means to the buyer
T1 is the first shot from the new mold, taken to check whether the steel produces the right part. T1 parts rarely meet everything. The buyer does not expect perfection at T1. The buyer expects to know exactly where the parts stand, what the plant thinks caused each gap and what it will do about it. The report is the plant’s record of that, and the basis for the next trial. For the full trial sequence see T1, T2 and T3 mold trials.
A report that answers these questions in one read earns trust:
- Which part, which revision and which mold?
- What was measured, with what, and what are the values?
- Which dimensions are out of tolerance, and why?
- What conditions made these parts?
- What happens next, and when?
The package: what to include
| Item | What the buyer needs to see |
|---|---|
| Cover sheet | Part number, revision, mold ID, cavity count, date, resin and lot, press, shot count, who made and who measured |
| Ballooned drawing | The buyer’s drawing with every dimension numbered, matched to the table |
| Dimension report | Nominal, tolerance, measured value per part and cavity, pass or fail |
| Material certificate | Resin grade, color, lot, supplier |
| Process sheet | The settings used for these parts |
| Photos | Parts, gate area, cosmetic faces, problem areas, mold open |
| Cosmetic and function check | Appearance against the agreed standard, fit on mating part or gauge |
| Deviations and actions | Each problem, probable cause, planned correction |
| Packing and labeling | How parts are marked by cavity |
Send it as a PDF for reading and a spreadsheet for sorting, with the same data in both. Use English and the buyer’s units.
The cover sheet
Put the identity of the parts first. It saves time when reports from several trials stack up in an inbox. Include:
- Part number and drawing revision, and the revision of the mold design.
- Mold ID or number, number of cavities and cavity numbering with a sketch of the layout.
- Trial name (T1), date and shot count when the samples were taken.
- Resin name, grade, color, lot number and drying done.
- Press used, with tonnage and screw size.
- Names of the person who ran the trial and the person who measured.
The ballooned drawing
A ballooned drawing is the buyer’s drawing with each dimension and note marked by a number in a circle. Every number appears as a row in the report. Do not reinterpret the drawing, and do not skip features that look hard to measure. If a dimension cannot be measured, say so and propose a method.
Keep the balloon numbers the same across all trials. That lets the buyer compare T1 and T2 by number.
The dimension report
This is the core of the package. A good table has:
- Balloon number and drawing reference.
- Nominal value and tolerance, in the drawing’s units.
- Measured value for each part and each cavity.
- Pass or fail, with out of tolerance cells highlighted.
- Measurement tool and method, such as CMM, vision system, gauge, caliper or micrometer.
Measure parts under the condition the buyer expects. Many resins change dimensions for hours or days after molding. State how long the parts rested and at what temperature before measuring. See injection molding tolerances for tolerances that depend on resin and part size, and POM acetal injection molding for an example where stabilization matters.
Also keep these habits:
- Use the same number of decimals as the drawing, plus one.
- Never round a failing value so that it passes.
- Record the gauge or machine used, and keep its calibration record available.
- Measure from the datums on the drawing, not from convenient edges.
Related guidance on first parts is in first article inspection for plastic parts.
Run an injection molding plant? Join as a partner factory
The process sheet
The process sheet records how the parts were made, so the next trial can change one thing at a time. Include:
- Melt temperature, barrel zones and nozzle temperature.
- Mold temperature for core and cavity, and coolant flow if measured.
- Injection speed profile, injection pressure limit and switchover point.
- Holding pressure and time.
- Cooling time and total cycle time.
- Screw speed, back pressure and shot size, with cushion.
- Hot runner temperatures, if used.
- Drying temperature and time for the resin.
If the buyer has a standard form, use it. Otherwise a clean one-page table is fine. Treat this sheet as a baseline, because later changes should be recorded against it. See process change notification for molded parts.
Photos that help
Photos reduce back-and-forth. Include:
- All parts laid out and labeled by cavity.
- Close-ups of cosmetic faces under good light, and of any defects.
- The gate area and runner.
- Short shots or flash if present, showing where they are.
- The open mold, core and cavity, if the buyer wants to see surface condition.
- A scale or a coin in each close-up so size is clear.
Name files with part number, trial and cavity. Do not send photos with no label.
Deviations and actions
This section tells the buyer you understand the problems. For each out of tolerance item or defect, write:
- The balloon number or defect name.
- The measured result and the requirement.
- The probable cause, in one or two plain sentences. Distinguish part design, mold, process and material causes. See injection molding defects: causes and fixes.
- The planned correction, such as a steel change or a process adjustment, and the date.
- Whether the buyer’s approval is needed. For example, a dimension may need a drawing tolerance change, not a mold change.
Example of a clear line: “Balloon 14, hole diameter 5.00 +0.05 / -0.00 mm. Measured 4.93 to 4.95 mm, all cavities. Cause: shrinkage lower than the value used for steel. Action: remove 0.06 mm from the core pin, which is steel-safe. Planned before T2.”
The wording is short and the action is specific. Avoid phrases like “will improve” or “under study”.
Packing the samples
The report travels with the parts, and also by email on the shipping day.
- Pack parts by cavity in labeled bags.
- Put a copy of the cover sheet in the box.
- Add parts from the best cavity for a separate fit check, if asked.
- Photograph the packed box before it ships.
- Send tracking details and the report in the same email.
Late sample reports slow the buyer’s approval and the schedule. See win overseas injection molding customers for what else overseas buyers look at when they judge a new plant.
Common mistakes
- Reporting only a few dimensions “that matter” instead of all.
- Mixing parts from different cavities in one column.
- No resin lot number, so a later resin problem cannot be traced.
- Different drawing revision from the buyer’s.
- Photos without labels.
- Out of tolerance values left unexplained.
- Changing the report format between T1 and T2.
For plants that want overseas buyers
plasticmoldingfactories.com is a manufacturers’ representative for audited plastic injection molding plants. Plants pay us a commission on orders from buyers we introduce, with no signup fee, and buyers pay nothing. Plants that are ready to be matched to a lane can apply through for factories, with no promise of orders.
Frequently asked questions
How many T1 parts should a plant measure?
Follow the buyer's request. A common starting point is a handful of parts from each cavity, measured on all drawing dimensions, but the buyer sets the number. If the request is missing, ask before measuring. If the mold has many cavities, ask whether every cavity must be reported.
Should the report hide dimensions that are out of tolerance?
No. Report every measured value, mark out of tolerance items clearly and explain the cause and the planned correction. Buyers trust a report that shows problems and a plan far more than one that shows everything in tolerance and then fails at assembly.
Does a T1 report need Cpk values?
Usually not. T1 is the first trial, with few parts and an unsettled process, so capability studies come later with larger samples. Include Cpk only if the buyer asks, and say how many parts it is based on.
Run an injection molding plant?
We represent audited plants to overseas buyers. No signup fee, commission only on orders from buyers we introduce. We reply within 24 business hours.
Join as a partner factory