PPAP, the Production Part Approval Process, is a package of records that a supplier submits to show a customer that its process can make a part to specification at production rate. For injection molded parts it means the plant proves the mold, the resin and the process by sending samples, measurements, capability data and control documents before full production begins. PPAP comes from the automotive industry and is managed by the AIAG, but buyers in other sectors borrow from it.
If your customer asks for PPAP, you need your molding plant to deliver it. This post explains what the package contains, how the levels differ, what changes for molded parts and how to set it up in the PO.
The 18 PPAP elements
The AIAG PPAP manual (4th edition) lists 18 elements. A given submission may need all of them or only some, depending on the level.
| No. | Element | Molding note |
|---|---|---|
| 1 | Design records | Drawing and 3D model, with a ballooned drawing |
| 2 | Engineering change documents | Change notices that affect the part |
| 3 | Customer engineering approval | If required by the customer |
| 4 | Design FMEA | Usually from the design owner |
| 5 | Process flow diagram | Resin drying to packing, including secondary operations |
| 6 | Process FMEA | Failure modes at each step, such as short shot, flash, sink |
| 7 | Control plan | What is checked, how often and the reaction plan |
| 8 | Measurement system analysis | Gauge R&R for the gauges used on critical dimensions |
| 9 | Dimensional results | Measured values from the sample parts, by cavity |
| 10 | Material and performance test results | Resin certificate, plus any required tests |
| 11 | Initial process studies | Capability study on key characteristics |
| 12 | Qualified laboratory documentation | Lab scope and accreditation if outside labs are used |
| 13 | Appearance approval report | For parts with color, grain or gloss requirements |
| 14 | Sample production parts | The parts themselves |
| 15 | Master sample | A signed sample kept as the reference |
| 16 | Checking aids | Fixtures, gauges, templates used for inspection |
| 17 | Customer-specific requirements | Anything extra from your customer |
| 18 | Part Submission Warrant (PSW) | The signed cover form |
The five submission levels
The level states how much of the package goes to the customer and how much stays at the supplier.
| Level | What is submitted |
|---|---|
| 1 | PSW only (and an appearance report where needed) |
| 2 | PSW with product samples and limited supporting data |
| 3 | PSW with product samples and complete supporting data |
| 4 | PSW and other items defined by the customer |
| 5 | PSW with samples and complete supporting data, reviewed at the supplier’s site |
Level 3 is the default unless the customer says otherwise. Your customer’s supplier manual sets the level, so do not assume it.
What changes for injection molded parts
PPAP was written for any manufactured part. Molding adds specific points to handle.
Cavity identification
A multi-cavity mold makes several versions of the same part. Each cavity can differ by a few hundredths of a millimeter. The dimensional results should be reported per cavity, and each part should carry a cavity number molded in or marked. If a cavity later fails, you must be able to trace the part back.
Sample size
The dimensional layout is usually reported on a small number of parts per cavity, often 5 to 30, depending on the customer. For a multi-cavity mold the plant may measure a few parts from every cavity. State the sample count you want in the PO.
Capability study
The initial process study is usually based on a significant production run, commonly quoted as 300 consecutive pieces or the output of a defined production period. Typical acceptance guidelines are a Ppk of at least 1.67 for the initial study and a Cpk of at least 1.33 for ongoing control, but your customer’s manual may differ. Check it. For how these indices are calculated and read, see Cpk in injection molding.
Plastic parts shrink and warp, so some dimensions cannot hit capability targets without changes to the part or the tolerance. Raise this at the design stage. See injection molding tolerances and GD&T for molded parts.
Material records
Include the resin certificate of analysis, the lot number used for the PPAP samples, the drying record and any colorant or masterbatch lot. If your drawing calls for a flame rating or food-contact compliance, include the supporting declarations. See resin lot traceability records.
Process documentation
The process sheet is part of the control plan. It should show the settings used for the approved samples: temperatures, injection speed and pressure profile, hold, cooling time, cycle time and the press used. These become the reference for future runs. Later changes should follow a process change notification. See process change notification for molded parts.
Appearance and secondary operations
If the part has a texture, color match or cosmetic standard, the appearance approval report records what was agreed. Secondary operations such as pad printing, assembly or ultrasonic welding need their own steps on the flow diagram, FMEA and control plan.
Need a quote for a molded part? Get matched with a molding plant
How PPAP relates to T1 samples and FAI
The trial rounds of a new mold (T1, T2, T3) come first. They are about getting the mold right. PPAP comes after the final approved trial and records that the production process, not just the mold, is ready.
- T1 sample report: early dimensional and visual check. See T1 sample report for export buyers.
- First article inspection: a full check of every drawing dimension on a first part. See first article inspection for plastic parts.
- PPAP: the full package for a production-ready process, including capability.
If your sector does not require PPAP, a good approval path is T1 report, FAI and a short capability study on the three or four critical dimensions.
What to put in the RFQ and PO
Do not leave PPAP for later. It affects the price and the lead time.
- State the level, and say which edition of the manual applies.
- State the customer’s supplier manual or attach it, if the customer has one.
- List the key characteristics and the capability targets for each.
- Set the sample counts per cavity.
- Name the due date for the submission relative to mold completion.
- Say who pays for outside lab tests or extra measurements.
- Require cavity marking on parts.
- Ask for the plan: which person at the plant owns the submission.
Questions to ask a plant
- Have you submitted PPAP before, and at which level?
- Do you have an in-house measuring room, or do you use an outside lab?
- Which gauges will you use on the critical dimensions, and how do you run the gauge study?
- How many pieces do you run for the capability study?
- Who prepares the FMEA and control plan, and can we review them before the run?
A plant that has not done PPAP before can still deliver it, but plan more time, give clear templates and check early drafts.
Common reasons a PPAP is rejected
- Dimensions reported as an average with no per-cavity data.
- Capability study done on too few parts or on a run that was not representative.
- Gauge study missing or the gauge resolution too coarse for the tolerance.
- Control plan that does not match the process flow.
- Drawing revision on the report different from the current release.
- Missing material certificate or resin lot record.
For the standard text itself, the AIAG website lists the current manual. Read the customer’s own requirements before you brief the plant.
If you need a plant that can deliver a PPAP package for a new part, send your RFQ with the level and the manual noted. We are a manufacturers’ representative, so we route the package to a partner plant whose lane fits the part. It costs buyers nothing. The plant pays us a commission on orders from buyers we introduce, and you order directly from the plant.
Frequently asked questions
Do I need PPAP for a non-automotive molded part?
Not formally. PPAP comes from the automotive supply chain and applies when your customer requires it. For other sectors a first article inspection, a T1 sample report and a control plan cover similar ground. You can still borrow parts of PPAP, such as the control plan and capability study, for any critical part.
How long does a PPAP take after the mold is finished?
It depends on trial rounds, the production run needed for the capability study and the lab work. A plant often needs a few weeks after the final sample approval, and longer if material testing or a long capability run is required. Ask the plant for a dated plan when you place the mold order.
What is a Part Submission Warrant?
The Part Submission Warrant, or PSW, is the cover form of a PPAP package. The supplier signs it to state that the parts meet all drawing and specification requirements and that the supporting records are attached. It is the document the customer approves or rejects.