Mold design review checklist: what to approve before the plant orders steel
November 16, 2026
A mold design review checklist is the list of items a buyer approves in the plant’s 3D mold layout before the plant orders steel and starts machining. The aim is to find expensive surprises while they are still a drawing change: the parting line on a cosmetic face, a gate in the wrong place, ejector pins that mark a visible surface, too few cooling circuits. After steel is cut, each of these becomes welding, inserts and delay. This page gives a practical checklist you can send to the plant and use as a sign-off record.
When the review happens
The sequence on a typical program is: RFQ, quote, order, DFM feedback on the part, mold design, mold design review, steel order, machining, assembly, T1 samples. DFM feedback is about your part. The mold design review is about the mold the plant plans to build. You approve the layout, and the plant builds it.
Ask for the review package on the day you place the order and agree on a date for it. The package normally holds:
- 3D mold layout in a neutral format, and a 2D assembly drawing.
- Cavity and core views showing parting line, gate, runner, ejectors, slides and lifters.
- Cooling layout showing circuits, inlets and outlets.
- Steel list with grade and hardness for cavity, core, slides and inserts.
- Bill of materials for standard components such as mold base, hot runner and ejector sets.
- Mold flow report if the plant has run one. See mold flow analysis.
If a plant cannot show these before cutting steel, treat it as a warning about how the mold will be controlled later.
The checklist
Work through it in this order. Mark each line approved, query or change request.
1. Part and layout
- Part revision in the mold design matches the revision you released. Write the revision on the review record.
- Shrinkage factor used for the resin, with the value stated. Plants set it from experience with the resin and the part shape; compensate for the right grade, not a similar one.
- Number of cavities is the number agreed in the quote. See how many cavities an injection mold needs.
- Cavity layout is balanced, so every cavity fills at the same time. A family layout, where different parts share one mold, needs a clear reason.
- Mold size fits the press the plant plans to use, including tie bar spacing, shut height, open stroke and clamp tonnage.
2. Parting line and cosmetics
- Parting line location is marked on the drawing and agrees with your cosmetic zones. Circle the faces that must stay clean.
- Shut-off surfaces, where the cavity and core touch to seal around a hole or window, have enough angle and land. Many guidelines ask for roughly 3 degrees or more on shut-off faces, but the mold maker sets the final value.
- Draft is present on all faces that need it, and textured faces carry extra draft. See draft angle in injection molding.
- Texture or polish is marked per face, using a named standard.
3. Gate and runner
- Gate type and location are shown and match your cosmetic and strength zones. A gate vestige on a visible face is a cosmetic decision. See injection molding gate types.
- Gate size is stated, and a note shows whether it can be enlarged later. Steel can be removed but is hard to add.
- Runner is cold or hot. If it is hot, ask for the supplier and the nozzle type, and who services it. See hot runner vs cold runner.
- Weld line locations from the flow report fall away from the load path and cosmetic faces.
4. Ejection and release
- Ejector pin positions, diameters and travel are shown. Pins leave witness marks, so none should sit on a visible face. See ejector pin marks.
- Ejection force is spread so thin walls and ribs do not distort.
- Sleeve or blade ejectors are used where pins would damage thin bosses or ribs.
- Return pins or a positive return system keep the ejector plate safe on closing.
- Slides and lifters are shown with their stroke, locking and wear plates. Ask which undercuts drive them. See undercuts in injection molding.
5. Cooling
- Cooling circuits cover core and cavity, with channels placed close enough to the surface to control temperature.
- Deep cores, thin pins and bosses have baffles, bubblers or a conductive insert if channels cannot reach.
- Water inlets and outlets are marked, easy to reach and not obstructed by clamps.
- Typical channel diameters for small to mid molds are around 8 to 12 mm, but the plant chooses on mold size and part geometry. See mold cooling design.
6. Venting
- Vents are shown at the end of fill, at weld lines and at deep ribs, with depth stated per resin. Typical vent depths are in the hundredths of a millimeter, set by the resin viscosity.
- Parting line and ejector pin clearances help venting but can also create flash on low viscosity resins. Ask for a note on how the plant will manage both.
7. Steel and build quality
- Cavity and core steel grade and hardness are stated. A surface treatment, such as nitriding or plating, is noted where used. See P20 vs H13 mold steel.
- Inserts at wear points, such as gate areas and slides, are replaceable.
- The mold is steel-safe on critical dimensions, so corrections remove steel rather than add it. See steel safe injection mold.
- Mold base uses standard components. Ask the plant to list the standard supplier so spare parts are easy to buy.
8. Marking and handling
- Part number, cavity numbers, date or shot counter and resin code are marked in the agreed places. The mold nameplate carries your company name and part number.
- Lifting holes are fitted for the mold weight. Water fittings and clamp slots are shown.
- Mold weight and dimensions are stated for freight and storage.
9. Paperwork and approval
- Review record is signed by both sides, with the revision and date.
- Change control: any later change to gate, parting line, cavity count or steel needs written approval.
- Sample plan is confirmed: T1 date, number of parts, measurement report and photos. See T1, T2 and T3 mold trials.
- Ownership and release terms are in the PO. See mold ownership agreement.
How to run the review
Send comments as one numbered list, not a stream of emails. Mark each item with a priority: must change before steel, should change or note only. Ask the plant to answer each point in writing, and to update the layout and resend it. Do not approve a layout that still shows the earlier version of any item.
If the plant explains why something stays as designed, take it seriously. Many plants have seen the resin and the geometry before. A good answer gives a reason with numbers, such as “the gate is here because the flow report shows balanced fill and the weld line lands on a rib”. A weak answer repeats “it is normal”.
Need a quote for a molded part? Get matched with a molding plant
What a plant should expect to hear
For a plant, the review is also a chance to avoid rework. Buyers who send clear cosmetic zones, tolerance priorities and volume forecasts make the mold design easier to finish in one pass. Spending a few hours on the review costs far less than a second round of sampling. For the cost side of tooling decisions, see injection mold tooling cost.
Get the part quoted with a review built in
plasticmoldingfactories.com is a manufacturers’ representative for audited plastic injection molding plants. Buyers pay nothing; the plant pays us a commission on orders from buyers we introduce. Ask for a design review step in your RFQ and we route it to the one partner plant whose lane fits, and you work through the review with that plant directly.
Frequently asked questions
How long should a mold design review take?
The plant usually sends the 3D mold layout a few days to two weeks after the order, depending on part complexity. Give your comments in one consolidated list within a few working days. A review that drags on holds the whole schedule, but a rushed sign-off is the more expensive mistake.
Do I need mold flow analysis before I approve the design?
It is not mandatory, but it is worth asking for on parts with long flow paths, thin walls, cosmetic faces or tight warpage limits. The report shows fill pattern, weld line locations, air traps and pressure, and it supports the gate decision.
What happens if I find a problem after steel is cut?
Removing steel is easy and adding it is not. A change that needs welding or a new insert costs more and takes longer, and it may leave a visible mark on cosmetic faces. That is why the review happens before steel is machined.