How to prepare a mold design review with overseas customers

November 21, 2026

A mold design review is a meeting, with documents, where the plant and the customer agree on how the mold will be built before steel is cut. With an overseas customer the review has to work across time zones and languages, so the preparation does the work that a visit to the shop floor would do. Send a clear package a few days ahead and show the decisions that carry risk. Run the call from an agenda, then finish with a written list of changes and a signed approval that names the layout revision.

This post is for plant managers, sales engineers and mold designers who sell to buyers in the US, Europe, Japan and Korea. It describes what export buyers expect and how to prepare. It does not promise orders. It covers how to make the review something the buyer can approve with confidence.

Why buyers insist on a review

Changing a mold after steel is cut costs time and money. Adding material to a cavity is slow, and moving a gate or a cooling line can mean a new insert. A buyer who is thousands of kilometers away cannot walk the floor, so the design review is the main chance to catch a problem. Buyers who have been burned before may ask for a review even on a simple mold. A plant that comes prepared tells the buyer that it knows the part and the process.

What to send before the meeting

Send the package at least three to five working days before the call, so the buyer’s engineers can read it. Send it in files that open on any computer.

  1. Part DFM report. Walls, draft, undercuts, ribs, bosses, sink risk, tolerance concerns and each item the plant wants changed, with the reason and a sketch or image. See injection molding DFM.
  2. Mold layout drawing. Cavity count and arrangement, parting line, gate type and position, runner and sprue, ejection method, slides and lifters, cooling circuits, vents, steel grades and hardness, mold base size and standard components.
  3. 3D or 2D views of the cavity and core, with the parting surface and shut-off areas marked.
  4. Shrinkage assumption. The value used for the resin grade, the direction if the plant applies it by direction and any dimension where the plant expects difficulty.
  5. Gate and cosmetic map. Gate location, ejector pin locations, parting line position and weld line expectations, drawn on the part. Show which faces are cosmetic.
  6. Mold flow results, when used. See mold flow analysis.
  7. Texture and finish plan, per face.
  8. Open questions, listed as numbered items, each with a plant recommendation.
  9. Schedule, showing the review date, steel order, cutting, T1 date and the effect of any delay in approval.

Keep the layout in one revision with a number and date. Mark every drawing with the revision.

What the layout must show

Buyers look for the same points in every review. Make each one easy to find.

  • Parting line and gate. Show where they fall on the part, and how that compares with the buyer’s cosmetic faces. See parting line in injection molding and injection molding gate types.
  • Ejection. Show where pins, sleeves or a stripper plate will touch the part, and what marks to expect. See ejector pin marks.
  • Undercuts. Show each slide or lifter and what it forms. If the plant proposes to change the part to remove one, say so.
  • Cooling. Show the circuits, with hot spots such as bosses and thick sections. A mold without a cooling plan is a warning sign.
  • Venting. Show vent locations at the end of fill and at weld lines.
  • Steel and life. State the steel, the hardness, the expected life in shots and the class the plant has in mind.
  • Runner system. Cold or hot runner, with the hot runner type, the gate type and the effect on waste and cycle time.
  • Maintenance access. Show how the mold opens for service, and which parts are wear items.

If the buyer uses a checklist of its own, ask for it ahead of time and answer it point by point. Compare your package with the mold design review checklist.

Run an injection molding plant? Join as a partner factory

Running the call

Time zones decide the schedule. Vietnam is at UTC+7. A buyer in Japan or Korea is about two hours ahead. A buyer in central Europe is about five to six hours behind, depending on daylight saving. A buyer on the US east coast is about eleven to twelve hours behind, so a US morning call is a Vietnamese evening. Offer two or three time slots and confirm the local time for both sides in writing.

Use a short agenda:

  1. Introductions and the revision under review (5 minutes).
  2. Part changes requested by the plant, one by one (20 to 30 minutes).
  3. Mold layout walkthrough: gate, parting line, ejection, cooling, steel (20 to 30 minutes).
  4. Cosmetic and tolerance risks (10 minutes).
  5. Open questions and decisions (10 to 15 minutes).
  6. Next steps, dates and owners (5 minutes).

Practical points:

  • Share the screen and rotate the 3D model rather than describing it.
  • Put one technical person who can decide on the plant side, not only a sales contact. Buyers lose confidence when every answer is “I will check”.
  • Speak in plain terms, avoid shop jargon the buyer may not share, and confirm key words by writing them in the chat.
  • Do not say “no problem” about a risk. Say what the risk is, what the plant proposes and what it needs from the buyer.
  • Record the call if both sides agree, and write the notes yourself.

Recording decisions

The meeting itself decides nothing until it is written. After the call, send within one working day:

  • A list of decisions, each with the item number, the decision, the owner and the date.
  • The updated layout drawing, with a new revision number, if changes were made.
  • A list of open items and who must answer.
  • A request for written approval of the named revision.

Ask the buyer to reply with “approved” for a named revision, or to list the changes. Start cutting steel only after that reply. Keep all review packages, notes and approvals with the project file. They also protect the plant if a dispute arises later about what was agreed. For the handover documents that a buyer may later ask for, see mold ownership agreement.

Common mistakes

  • Sending the package the night before the call.
  • Showing a layout with no cooling lines or no vent positions.
  • Placing the gate on a cosmetic face without telling the buyer.
  • Using a shrinkage value with no reason behind it.
  • Asking the buyer to approve in the meeting, with no time to read.
  • Changing the layout after approval without a new revision.
  • Treating the buyer’s silence as consent.
  • Mixing up part changes (the buyer’s drawing) and mold choices (the plant’s decision).

What comes after the review

A good review shortens the trial phase. The first samples (T1) should then show only small corrections, not basic errors. Prepare the T1 report format at the same time and tell the buyer what will be measured. See T1, T2 and T3 mold trials and T1 sample report for export buyers. For the wider picture of what export buyers expect, read how to win overseas injection molding customers.

If you run a molding plant and want overseas buyers to find you, see for factories. We are a manufacturers’ representative. We introduce buyers to the one partner plant whose lane fits their part. There is no signup fee, the plant pays a commission on orders from buyers we introduce, and we cannot promise orders.

Frequently asked questions

How long before steel is cut should the mold design review happen?

Early enough that a change is cheap. Most plants hold the review once the mold layout and the part DFM report are ready, and before any steel is ordered or cut. Give the customer several working days to read the package, and leave time for a second round if the first raises changes.

What if the customer does not reply to the review package?

Do not treat silence as approval. Send a short reminder with the exact items awaiting a decision and a date after which the schedule will slip. Record the delay. Start steel only on a written approval that names the layout revision.

Should the plant show mold flow results in every review?

For parts with thin walls, long flow paths, tight tolerances, cosmetic faces or multiple gates, yes. For a simple part, a short fill and gate note may be enough. Offer the analysis when the risk justifies it and say clearly what it does and does not predict.