15 questions to ask an injection molder before you place the PO
November 5, 2026
The questions to ask an injection molder before a PO are the ones that expose how the plant actually works: which presses it will use, who owns the mold, how it proves parts are good and what happens when something changes. A quote shows price. These questions show risk. Below are 15, grouped by topic, each with what a useful answer sounds like. Send them in writing with your RFQ package and keep the replies in the project file.
Capability: can this plant run your part?
1. Which press will run this part, and what are its tonnage and shot size? A good answer names a specific press or press class, for example “a 150 ton machine with a shot capacity that fits the part at 40 to 70 percent of barrel”. A press that is too large wastes money. One that is too small risks flash, short shots or a worn screw.
2. Have you molded this resin before, and which grade? Resin families behave differently. Glass filled nylon, polycarbonate and POM each need specific drying, barrel and mold temperature control. Ask for the dryer type and the drying settings the plant would use. See the resin drying temperature chart for typical values you can check against.
3. What similar parts do you run today, and what is the tightest tolerance you hold on molded features? Ask for the part type and size range, not a customer name. A plant that molds thin wall packaging may not be the right lane for a thick, tight tolerance housing. Match the part to the plant’s lane.
4. What happens if my volume doubles or halves? Ask how the plant would add capacity or move the mold to another press. The answer shows whether the plant has spare capacity or is already running full.
Tooling: who builds, owns and maintains the mold?
5. Is the mold built in house or by a partner tool shop? Both can work. What matters is who is responsible when the mold needs a correction. In house tooling usually shortens correction time. A partner shop needs a clear line of responsibility. Ask who carries out a design review and who signs off.
6. What steel will the cavity and core use, and what mold life do you expect? Expect a grade and a shot count, such as P20 pre-hardened for moderate volumes or a hardened steel for long runs. Compare with P20 vs H13 mold steel if the answer is vague. A low quote often means softer steel.
7. Who owns the mold, and how is it released if I move production? The answer should be “you own it”, followed by a marking and release procedure. If the plant hesitates, read mold ownership agreement clauses before you pay a deposit.
8. Who pays for mold maintenance and repair, and after how many shots? A reasonable plant covers routine maintenance as part of its process and quotes repairs caused by normal wear separately. Get the split in writing, including who keeps spare inserts and ejector pins.
Quality: how does the plant prove parts are good?
9. What will you send me at T1, and which dimensions will you measure? A good answer lists a dimensional report against a ballooned drawing, photos, material certificate and process record. The T1, T2 and T3 mold trials article explains what each round should deliver. Ask how many parts per cavity are measured.
10. What inspection equipment do you have, and how is it calibrated? Ask for the list: calipers, pin gauges, a CMM or vision system and the calibration schedule. A plant that sends critical dimensions to an outside lab can still be a good choice, if it says so.
11. How do you control resin lots, regrind and color? You want lot numbers recorded against production dates, a stated regrind percentage (or none) and a color check method. Regrind limits should match what you approve on the drawing or PO. Details are in resin lot traceability records.
12. How do you handle a change to mold, material or process? The right answer is a written notice and your approval before the change. The plant should not switch resin grade, move a mold to a different press or alter a validated setting without telling you. See process change notification.
Commercial: what exactly are you paying for?
13. What is included in the mold price and the piece price? Ask for a list: design review, number of sample rounds, spare parts, packaging, inspection and any resin price adjustment clause. Use the checks in how to compare injection molding quotes so two quotes mean the same thing.
14. What are your lead times for the mold, first samples and a repeat order? Expect separate numbers for design, tool build, T1 samples, corrections and production. Typical mold lead times run several weeks to a few months depending on size and complexity, and the plant should state its own. A single “30 days” for everything is not an answer.
15. What are your payment terms, minimum order quantity and Incoterm? Typical terms split the mold payment into a deposit, a sample milestone and a final payment, and tie production payments to shipment documents. Ask what the MOQ is and why. Agree the Incoterm for the first shipment in the PO.
Need a quote for a molded part? Get matched with a molding plant
How to use the answers
Put the 15 questions in a table, one column per plant, and score each answer as clear, partial or missing. Do not add up a total and pick the winner. Look instead for the question where a plant is weakest and ask whether you can live with that gap.
| Answer type | What it sounds like | What to do |
|---|---|---|
| Clear | A number, a document name or a role | Note it and move on |
| Partial | “Usually” or “depends” with no detail | Ask a follow up in writing |
| Missing | No reply or a change of subject | Treat as no, until shown otherwise |
A few answers should be settled before you spend money on a mold: ownership, steel and life, what T1 delivers and how changes are approved. Those four are expensive to fix after the mold is cut.
Questions to add for special cases
Some programs need more than the 15 questions above. Add these when they apply:
- Cosmetic parts: How do you control color from lot to lot, and do you keep a master color sample? Who approves the cosmetic limit samples?
- Assembly or secondary work: Do you do pad printing, ultrasonic welding or assembly in house, and what inspection follows each step?
- Medical, food or electrical use: Which resin approvals and declarations can you supply for the grade and color? Do you keep a clean area for the product?
- High volume: How do you plan maintenance on the mold, and what is the spare parts list?
- Export shipping: How do you pack, label and document the shipment, and who books freight?
Ask for evidence, not promises
For each answer, ask for one document. A sample inspection report for the press and process answers. A mold tag photo for ownership. A calibration record for the gauge answers. A blank change notice form for the change control answer. A plant with real systems will send these in a day or two. A plant that builds them after you ask will take longer, and that delay tells you something.
Keep the replies. When a problem appears six months later, the written answer to “who approves a process change” settles the discussion faster than any meeting.
For a wider screen of plants before you ask these questions, start with how to choose an injection molding factory, and prepare the quote package using what to send for an injection molding RFQ.
Send the part to a matched plant
We are a manufacturers’ representative for audited plastic injection molding plants. Buyers pay nothing: the plant pays us a commission on orders from buyers we introduce. Send your RFQ with the drawing, resin, volume and finish, and we match it to the one partner plant whose lane fits. You then order from that plant directly.
Frequently asked questions
Should I ask these questions before or after I receive a quote?
Ask the capability and tooling questions before you request a quote, so you only quote plants that can run the part. Ask the commercial and quality questions once you have a quote in hand, because the answers explain what is and is not inside the price.
What is a red flag in a plant's answers?
Vague answers to specific questions. If you ask for the steel grade and get 'good steel', or ask how a process change is approved and get 'we always tell you', the plant has no written procedure. A good plant answers with a number, a document name or a person's role.
Can I send the same questions to every plant?
Yes, and you should. Identical questions give you comparable answers. Send them as a short written questionnaire with your RFQ package and ask for replies in writing, so you can compare them side by side and keep them on file.