Injection molding cost per part: how the piece price is built, line by line

October 27, 2026

Injection molding cost per part is the sum of material, press time, labor, scrap, packaging, overhead and margin, divided by the good parts made. For most plastic parts, material and press time make up the large majority of it. Mold cost is normally separate, quoted once. If you understand the five or six lines inside a piece price, you can read any quote, see why two plants differ and know which design or process choices will move the number.

The lines inside a piece price

Line What it covers What moves it
Material Part weight, runner and sprue share, purge, scrap allowance, resin price Resin grade, part size, cold or hot runner
Machine time Cycle time multiplied by the press hourly rate, divided by cavities Wall thickness, cooling, press size, cavity count
Labor Operator, material handling, trimming, inspection, packing Automation, part complexity, inspection plan
Secondary operations Degating, assembly, printing, ultrasonic welding, inserts Design and cosmetic requirements
Packaging Cartons, bags, trays, dividers, pallets Cosmetic sensitivity, export route
Overhead and margin Plant costs not charged elsewhere, profit Plant, region, order size, relationship

Freight, duty and your own quality costs sit on top of the piece price and belong in your landed cost, not in the plant quote.

Material: usually the biggest line

Material cost is the weight of plastic used per good part multiplied by the resin price per kilogram. Three things sit inside the weight.

  • Part weight. From the CAD volume and the resin density.
  • Runner share. In a cold runner mold, the sprue and runners are ejected with the parts. They are reground and reused in some cases, but often limited by the application and your specification. In a hot runner mold this waste is close to zero.
  • Scrap allowance. Startup shots, purging between colors, rejected parts. Plants add a percentage, often a few percent for stable processes and more for difficult materials or cosmetic parts.

Resin prices move with oil, feedstock and supply. Commodity resins such as PP and HDPE sit at the low end per kilogram. Engineering resins such as PC, PA and POM cost more. High-performance resins such as PEEK cost many times more. Because the price changes, many plants quote with a resin price basis and a surcharge clause. Read that clause: it decides who carries a price swing.

If you are open to regrind, say how much. Regrind lowers material cost, but some applications (food contact, medical, optical parts) do not allow it, and some specifications cap it.

Machine time: where design shows up

Machine time per part is cycle time times the press hourly rate, divided by the number of cavities. Cycle time is made of injection, packing, cooling and mold open, ejection and close. Cooling is usually the longest part, and cooling time grows roughly with the square of the wall thickness. A 3 mm wall can need several times the cooling time of a 1.5 mm wall.

This is why wall thickness is the cheapest design lever you have. Thinning a section from 3 mm to 2 mm, if strength allows, can cut cycle time a lot. The details are in injection molding cycle time calculation.

Press hourly rate depends on tonnage, the plant’s cost base and utilization. A larger press costs more per hour, so a plant will choose the smallest press that holds the mold and gives enough clamp force. Rates vary a lot between regions and plants, so injection molding machine hourly rate looks at what sits inside that number.

Labor, secondary operations and packaging

A fully automated cell with robot take-out and in-line inspection needs little labor per part. A manual process needs an operator to remove parts, trim gates, check them and pack them. For small parts the labor line can be a few percent of the price. For parts with assembly, ultrasonic welding, pad printing or inserts, it can match the molding cost.

Ask what is included. A piece price that excludes degating, in-process inspection or individual bagging is not comparable with one that includes them. See injection molding secondary operations for the common add-ons.

Packaging is small per part but adds up on large or cosmetic parts. Export packaging needs strong cartons, pallets and sometimes humidity protection, which costs more than a domestic delivery.

A worked example

The figures below are illustrative assumptions, not a quote. They show how the lines combine.

Assumptions: a small ABS housing, 25 g part weight, 4-cavity cold runner mold, 3 g of runner per shot shared across cavities (about 0.75 g per part), resin at 2.20 USD per kg, cycle time 30 seconds, press rate 25 USD per hour, packing and labor 0.01 USD per part, overhead and margin 20 percent.

  1. Material: 25.75 g at 2.20 USD per kg is 0.057 USD. With a 3 percent scrap allowance, about 0.058 USD.
  2. Machine time: 30 seconds per shot over 4 cavities is 7.5 seconds per part, so 480 parts an hour. At 25 USD an hour that is 0.052 USD per part.
  3. Labor and packing: 0.010 USD.
  4. Subtotal: about 0.12 USD.
  5. Overhead and margin at 20 percent: about 0.14 USD per part.

Now change one thing. If the same part ran in a single cavity at the same cycle time, machine time per part would be four times higher: 0.208 USD. The piece price would rise to roughly 0.33 USD. The mold would be cheaper, but the parts would cost more than twice as much. That trade-off is why cavity count follows volume, and why how many cavities your mold should have matters before you sign off the mold.

Need a quote for a molded part? Get matched with a molding plant

Mold cost and piece price together

Mold cost and piece price trade against each other. A cheaper mold with fewer cavities or a cold runner raises the piece price. A more expensive mold with more cavities and a hot runner lowers it. The right answer depends on total volume over the program.

A simple way to compare: total cost = mold price + (piece price x total parts). Run it for two or three options at your forecast volume, and again at half the volume to see how sensitive it is. Our article on injection mold tooling cost lists what drives the mold side.

Order size and tooling amortization

Small orders cost more per part for two reasons. Each run has fixed setup: material changeover, mold change, press warm-up, first-piece approval. Spread over 500 parts it is large per part. Over 50,000 it nearly disappears. Also, plants rank small orders behind large ones when scheduling presses, so lead time can slip.

If your volume is low, say so up front. Some plants specialize in short runs and price them honestly. Others accept the order and add a setup fee later. See low volume injection molding cost for the trade-offs.

Ways to lower the piece price

In rough order of effect for most parts:

  1. Reduce wall thickness and make it uniform. Cuts cooling time and material.
  2. Increase cavities if volume supports the mold cost.
  3. Choose the resin for the job, not for habit. A cheaper grade that meets the requirement saves on every shot.
  4. Loosen tolerances that do not affect function.
  5. Limit cosmetic finish to the faces that show.
  6. Consolidate parts and operations, so fewer secondary steps are needed.
  7. Order in fewer, larger lots if cash flow and shelf life allow.

Avoid the false saving: asking a plant for a lower price without changing the part often means a shorter cycle than the process can hold, which shows up later as warpage, short shots or sink marks.

Getting a price you can trust

A trustworthy quote lists its assumptions: cavities, cycle time, resin and price basis, part weight, scrap allowance and what is excluded. When you request quotes, send the full package described in injection molding RFQ: what to send for a firm quote.

Broad ranges for piece prices are rarely useful, because a 5 g PP cap and a 300 g glass-filled housing share a process but not a price. Region, volume, resin and part decide, so ask for a quote on your actual part.

We are a manufacturers’ representative for audited plastic injection molding plants. If you want a quote from a plant whose press range and resin lane fit your part, send the RFQ. It is free for buyers; the plant pays us a commission on orders from buyers we introduce, and you place the order with the plant directly.

Frequently asked questions

Is mold cost included in the piece price?

Usually not. Most plants quote the mold as a separate one-time charge and the piece price for the parts only. Some plants offer to spread the mold cost over the first orders. If they do, ask for the amortization terms in writing, including what happens if you stop ordering before the mold is paid off.

Why does the piece price drop when I order more?

Setup cost is spread over more parts, material is bought in larger lots and the plant can plan longer runs on one press. Past a point the price stops falling, because material and machine time per part do not change. Ask for price tiers at several order quantities to see where that point is.

How do I check that a piece price is fair?

Ask for the assumptions behind it: cycle time, cavities, part weight with runner, resin price and press tonnage. Then check them. A cycle time that looks too short or a resin price below market means the price will rise later or the quality will drop. A plant that will not share assumptions makes comparison hard.